Generator and UPS Maintenance

Dear Customer,

TelecityRedbus will be carrying out a series of routine maintenance works within 6&7 Harbour Exchange Square as part of our ongoing PPM (planned preventative maintenance) programme. These works will take place between Monday 15th January and Wednesday 24th January as detailed below.

Generators
———–
15th January – generator maintenance

UPS

16th & 17th January – UPS system maintenance (level 8)

18th, 19th & 22nd January – UPS system maintenance (level 7)

Black Out Test
————–
24th January – building black out test.

A building black out test will be carried out upon successful completion of the Generator and UPS maintenance, to test the system as a whole ensuring it works as per its design. It is basically a mains failure simulation under tightly controlled conditions with facilities staff and specialist engineers on site. This test is designed to flag any potential issues within a controlled environment and will be carried out on a monthly rotating basis.

All works will be carried out between the hours of 08.00 – 18.00 on the allotted days.

These works should be viewed as medium risk.